TP_LogoMark@2x
Boiler Replacement at a Large Manufacturing Facility in Southern Ohio

News

Projects

Share

Boiler Replacement at a Large Manufacturing Facility in Southern Ohio

A 900,000 square foot manufacturing facility in southern Ohio recently hired TP Mechanical to replace two, 70-year-old boilers. TP not only completed this project in six weeks, but during the demolition and installation, there was no disruption to the manufacturing facility’s production.

TP replaced dated, inefficient boilers with a new hydronic boiler and steam boiler. The two boilers deliver energy efficient coverage for the entire facility, including a manufacturing area and several offices.

One benefit of the new steam boiler is during the winter months, the equipment can be easily be converted from burning natural gas to propane. This was a unique project requirement as during heating season, the owner will switch to propane for significant energy and cost savings due to the size of the facility. 

The Cincinnati service team did a phenomenal job keeping the project on track, while combatting shipping delays caused by the pandemic. Under the leadership of project manager, Scott McEvilly and lead pipefitter, Tony Schroder, the team overcame any obstacle they had little control over to complete the project in six weeks.

TP Team:

Scott McEvilly, Project Manager

Russ Shively & Adam Luensman, Sales Representatives

Tony Schroeder, Lead Pipefitter

Dennis Meredith, Equipment Tuner

Share:

Related Posts